1.0 Objective:
The objective of
this Standard Operating Procedure is to lay down the procedure for Operation and
calibration of Gas chromatography.
2.0 Scope:
This SOP covers
procedure for operation and calibration of Gas chromatography
Jr.
Research Officer, Research Officer: Responsible for operation and maintenance
of the
instrument as per procedure.
Head of Department: Responsible for maintenance, timely as per schedule.
QA Officer/QA Manager: Review the records and governing the document.
4.0 Procedure :
4.1
I. Ensure that the instrument is visibly
clean and free from dust.
II. The room temperature should be maintained between 10 to 30°C and
relative humidity Should be maintained between 30 to
80 %
III.
Avoid direct exposure to air-blow from air conditioners.
IV. Avoid exposure to direct sunlight and vibrations.
4.2 Install properly
suitable capillary column in GC oven injector & selected detector.
4.3 Open the valve of gas cylinder of Nitrogen, Hydrogen and
z-Air. And checked the pressure & leakage.
4.4 Open the Gas pressure valve from the distribution panel.
4.5 Check the
backpressure of column.
4.6 Switch on the mains
power, stabilizer, GC power & computer power.
4.7 Double click on the instrument1 (online)
& instrument1 (offline) icon from the desktop; create new method
from instrument1 (offline) and load method in instrument1 (online) from
file menu. Apply the chromatographic condition and enter ok. And view the run signal
window, After completion of the run, and open the instrument offline select the
file and
integrate the peak using integration menu, go to calibration task icon and
enter the component name
and click on ok, then print the chromatogram by clicking print option from file menu.
4.8 Condition the column at 280°C for 10 min.
Enter the programming condition of the sample
through micro syringe, when G.C shows ready signal.
4.9 Cool the G.C after completion of the analysis
& switch it off. Shut down the computer, mains power supply. Close the gas
supply from the distribution panel & from cylinder.
5.0 Routine Maintenance:
5.1 Clean the all out side part of
instrument.
5.2
Clean the injector and injector liner. Change the glass wool of injector liner.
Change the Septa of injector port if required.
5.3
Check the all connection of gases for
leakage.
6.0 Documentation:
Annexure-1 Gas Chromatography system usage
logbook XXX/FRM/000
Annexure-2 Gas Chromatography Routine maintenance
record XX/QF/000
7.0 History of Revision:
Revision No.
|
Effective
Date
|
Revision
details
|
Reason for
revision
|
GC USAGE LOGBOOK
|
|||||
Date
|
Name of sample
|
Booking No.
(A.R. No.)
|
Batch No.
|
Analyzed By
|
Remarks
|
SOP: XXX/SOP/000-00 Format No. : XXX/FRM/000-00
|
No comments:
Post a Comment