Phase-I: Develop & finalize operating procedure,
preventive maintenance and sanitization procedures. Demonstrate production
& delivery of water of required quality. To finalize SOP on sanitization of
the water system, Alert & Action limits. Phase – I is conducted for 14-28
days.
Phase-II: Demonstrate consistent operation
within established ranges. Demonstrate consistent production & delivery of
water of required quality (pharmacopeia). Phase – II is conducted for 14-28
days.
Phase-III: Demonstrate extended
performance of the water system. Ensure that potential seasonal variations are
evaluated & treated. Phase-III is conducted for 10-12 months.